Home → Blog → How Long Does a Kitchen Remodel Take in Chicago?
Updated November 2, 2026
On our projects, a kitchen remodel takes about 8 to 12 weeks to build once the design is final. See what speeds it up, what slows it down, and how to plan.
Marc Santarromana
In this article
How long does a kitchen remodel usually take? How does a kitchen remodel work, step by step? What makes a kitchen remodel take longer? What if my kitchen remodel includes an addition? How do I plan for life without a kitchen? How can I keep my kitchen remodel on schedule? Kitchen remodel timeline questionsOn our own projects, a kitchen remodel has taken about 8 to 12 weeks to build once the design is final. Your project manager sets the final schedule once your design and scope are complete, because design complexity, material lead times, and changes along the way all affect the timeline. Here’s what moves it and how to plan for it.
Our kitchen projects have taken about 8 to 12 weeks to build once the design is final. That’s a general range, not a promise. Your project manager gives you a detailed schedule once your design and scope are final.
Design and material selection come before construction starts, so plan for time ahead of the build as well. See Our Home Remodeling Process for the steps.
Design. A designer walks your space with you, then you review a floor plan, 3D concepts, and a cost breakdown. You can revise the design until it feels right.
Architecture and selections. Your drawings and specs are re-checked, you choose cabinets, countertops, flooring, and lighting with our interior designers, and materials are ordered.
Production. You meet your project manager before construction to review the schedule, work hours, and how your home will be protected. Your project manager then coordinates every trade, and the project ends with a final walkthrough.
Moving things. Layout changes add plumbing, electrical, and sometimes structural work. Kitchen Layout Types: Which Shape Fits Your Home? can help you decide before design starts.
Material lead times. This includes custom cabinets. Custom Cabinets: AnnTucker vs. Arbor Mills in Chicago compares our two options.
Late selections. How quickly you decide on finishes affects the total.
Older houses. Opening walls can reveal surprises. Remodeling an Older Home: What to Know Before You Start explains what to expect.
Changes mid-project. Change orders adjust the price, and sometimes the schedule.
If your kitchen project includes a bump-out or an addition, the addition sets the pace. On our projects, additions have run about 4 to 6 months, or 8 to 10 months with a second story. See our home additions page for more.
Set up a temporary kitchen before demolition starts. A small table with a microwave, a kettle, a coffee maker, and a mini fridge covers most households. Keep paper plates, utensils, and a few pantry basics close by. Ask your project manager at the pre-construction meeting when your kitchen will be out of use.
Make your selections early, especially cabinets, countertops, and fixtures.
Avoid changes once construction begins.
Review the schedule with your project manager before work starts.
On our projects, about 8 to 12 weeks to build once the design is final. Your project manager sets the final schedule once the design is complete.
Design and material selection happen before construction starts. The time they take depends on how quickly you make decisions, so choosing finishes early helps.
You will not have a working kitchen during construction, so set up a temporary one nearby. Your project manager reviews the schedule and how your home will be protected before work begins.
Tell us what you’d like to change, and we’ll help you decide where to begin.